HPG® High Performance Gravity® Natural Turf System Installation Process Case Study Field: GABBA Cricket Grounds Location: Brisbane, Australia 1. Excavation of existing field Note cricket wicket remained intact in the center of the oval |
||
![]() |
2. Drainage installation Installation of perimeter main perforated drainage pipe with tees installed to accept the lateral drains |
||
![]() |
3. Perforated lateral installation Perforated laterals being cut into laser prepared sub base |
||
![]() |
4. Additional lateral installation Laterals installed and backfilled over half the oval |
||
![]() |
5. Full lateral install Laterals fully installed in a herringbone pattern across the four quadrants of the oval |
||
![]() |
6. Gravel install Installation of USGA gravel raft over the sub base |
||
![]() |
7. Gravel install Gravel installation completed and laser leveled with wicket block protected in the center of the oval |
||
![]() |
8. Rootzone and laser grading USGA rootzone being installed over gravel layer and laser graded |
||
![]() |
9. TSII® grass sod installation Installation of TSII® big roll sod |
||
![]() |
10. Custom irrigation system Operation of custom designed irrigation system in conjunction with sod installation |
||
![]() |
11. Cricket Opening Day Cricket season opener, Australia versus North Africa |